Which part of a project management plan uses a Gantt Chart as a management tool? 0000 Scope Budget Schedule Risk
Roztwór
Rubén
professionell · Tutor durante 6 años
4.4
(268 Votos)
Respuesta
The correct answer is: Schedule.A Gantt Chart is a type of bar chart that represents the schedule of a project. It is commonly used in project management to visualize the start and finish dates of the various tasks and activities within a project. The Gantt Chart helps project managers track the progress of the project and ensure that all tasks are completed on time. Therefore, the part of a project management plan that uses a Gantt Chart as a management tool is the Schedule.