Pagina de inicio
/
Negocios
/
Which part of a project management plan uses a Gantt Chart as a management tool? 0000 Scope Budget Schedule Risk

Problemas

Which part of a project management plan uses a Gantt Chart as a management tool?
0000
Scope
Budget
Schedule
Risk

Which part of a project management plan uses a Gantt Chart as a management tool? 0000 Scope Budget Schedule Risk

Solución

avatar
Rubénprofessionell · Tutor durante 6 años
expert verifiedVerificación de expertos
4.4 (268 votos)

Responder

The correct answer is: Schedule.<br /><br />A Gantt Chart is a type of bar chart that represents the schedule of a project. It is commonly used in project management to visualize the start and finish dates of the various tasks and activities within a project. The Gantt Chart helps project managers track the progress of the project and ensure that all tasks are completed on time. Therefore, the part of a project management plan that uses a Gantt Chart as a management tool is the Schedule.
Haz clic para calificar: