Which part of a project plan is affected as a result of change that is approved through the change management process? 0000 Lessons learned Resource availability Project scope Project charter
Solución

Elizabethmaestro · Tutor durante 5 años

4.2 (210 votos)
Responder
The correct answer is: Project scope.<br /><br />When a change is approved through the change management process, it typically affects the project scope. The project scope defines the specific work that needs to be done to achieve the project objectives. Any changes to the project scope will impact the tasks, timelines, resources, and budget associated with the project. Therefore, it is important to update the project scope document to reflect any changes that have been approved.